Arms exporter Rosoboronexport will put off delivery of a renovated $2.3 billion aircraft carrier to India by five months to fix defects in its construction, a state shipbuilder said, blaming some of the problems on NATO-supplied equipment.
Sources close to Rosoboronexport said earlier this week that problems with the boilers on the Vikramaditya were discovered during sea trials and would delay delivery of the vessel by six months to a year.
The head of a top shipbuilder confirmed Friday that boilers had malfunctioned.
"Besides that, there are a series of mechanisms that malfunctioned, including those delivered by countries of NATO," Interfax quoted Andrei Dyachkov, president of United Shipbuilding Corp.
(Reuters)
Related articles:
A Message from The Moscow Times:
Dear readers,
We are facing unprecedented challenges. Russia's Prosecutor General's Office has designated The Moscow Times as an "undesirable" organization, criminalizing our work and putting our staff at risk of prosecution. This follows our earlier unjust labeling as a "foreign agent."
These actions are direct attempts to silence independent journalism in Russia. The authorities claim our work "discredits the decisions of the Russian leadership." We see things differently: we strive to provide accurate, unbiased reporting on Russia.
We, the journalists of The Moscow Times, refuse to be silenced. But to continue our work, we need your help.
Your support, no matter how small, makes a world of difference. If you can, please support us monthly starting from just $2. It's quick to set up, and every contribution makes a significant impact.
By supporting The Moscow Times, you're defending open, independent journalism in the face of repression. Thank you for standing with us.
Remind me later.